top of page

INDUSTRIAL

INDUSTRIAL CASE STUDY

Project Synopsis

A 5000 m2 hardstand was completed under a design and construct engagement for this institutional client.  In addition to the hardstand project, we also completed the largest privately funded sound wall, constructed in line with council requirements, meeting all acoustic and council zoning requirements.

 

Duration

4 months

INDUSTRIAL CASE STUDY

Project Synopsis

This industrial asset underwent a large upgrade before being released to the market.  Extensive hardstand and drainage works were required due to existing asphalt failing.  This project was undertaken under a design and construct consisting of more than 4500 m2 of new asphalt, drainage and line marking

 

Duration

2 months

DSC_9539_edited_edited.jpg

INDUSTRIAL CASE STUDY 

Project Synopsis

Due to site requirements, this client required the 

extension of the existing hard stand to accommodate B Double truck access.  Envisage Group where engaged under a design and construct from full planning design through to delivery resulting in a new 2000 m2 handstand with new civil drainage

Duration

2 months

DSC_9523_edited.jpg
DSC_9550_edited.jpg
DSC_8748_edited.jpg

INDUSTRIAL CASE STUDY - New Canopy and loading bay entrance

Project Brief

Envisage Group where appointed to complete a full turn key delivery for this institutional client.  This involved all planning, design and compliance works, ensuring the tenant brief was achieved.  Works consisted of new 600 m2 awning, including new transitional ramp, rapid and roller doors, civil works and all design responsibilities

 

Duration

4 months including planning

DSC_9550_edited.jpg
DSC_8748_edited.jpg
bottom of page